The project involves construction of a 2,500 square foot addition and interior alterations to the student center building. The scope of work includes but is not limited to site work, steel, concrete/masonry, electrical, plumbing, interior finishes, flooring, foodservice casework, kitchen equipment, and curtain wall. Bids will be received for a single lump sum contract covering all work indicated in the construction documents.
Mandatory Pre-Bid Meeting: 10:00 A.M. Thursday, March 31, 2016 in the Student Center room SC-158. If due to inclement weather the College is closed at this time, the pre-bid meeting and site inspection will be held on the next business day at the same place and time.
Last Day for Questions: Friday, April 8, 2016. Please send all questions via e-mail to Gregg Romero, Jr. – Cambridge Construction Management at gromerojr@cambridgecm.com.
Final Addendum to be issued: Wednesday, April 13, 2016.
Bid responses are due by: 2:00 P.M. Friday, April 22, 2016. Deliver bids to the Purchasing Department Academic Wing D room D-116
Contact: Gregg Romero, Jr. – Cambridge Construction Management at gromerojr@cambridgecm.com.
Please use Firefox, Safari or Chrome to download files.
Bid Documents: Specifications (zip), Ramapo Project Manual_BID SET (pdf)
Drawings (comprised of seven files): 01 – Plumbing Drawings – Student Center Phase 2 (pdf),
01 – Structural Drawings – Student Center Phase 2 (pdf),
03 – Mechanical Drawings – Student Center Phase 2 (pdf),
04 – Electrical Drawings – Student Center Phase 2 (pdf),
05 – Fire Protection Drawings – Student Center Phase 2 (pdf),
Architectual Drawings 1-25 (pdf)
Architectual Drawings 26-45 (pdf)
Pre-Bid Meeting and Site Inspection Sign-In Sheet: 2014-37-01C.1 Sign-In Sheet (pdf)
Addendum No. 1 is comprised of the following twenty files:
00 20 00 Instructions to Bidders – Addendum (pdf) 00 31 32-1 Geotechnical – Student Center Phase 2 (pdf)
00 40 00-1 Bid Cover Sheet – Addendum (pdf) 00 40 00-2 Proposal Form (pdf)
00 70 00-1 General Conditions (pdf) 01 11 00 Summary of Work (pdf) 01 23 00 Alternates (pdf)
01 31 00 Project Administration (pdf) 03-31-15 – SC Phase 2 – Prebid Meeting Agenda (pdf)
04-12-16 – Bid Addendum Summary – SC Phase 2 (pdf) 04-12-16 – New Steam and Condensate Line (pdf)
04-13-16 – Location of Temporary Partitions (pdf) 11-17-15 – Soils Test Report – Phase 2 (pdf)
2014-37-01C.1-Sign-In-Sheet (pdf) 230503 – Student Center Phase 2 (pdf)
Aerowerks Proposal for Addendum (pdf) Bid Addendum No. 1 Cover – SC Phase 2 (pdf)
Furniture Dwg showing location of fixed stools (pdf) Ramapo – Plans Addendum 1 (pdf)